Neosho Daily News - Neosho, MO
  • Summer projects get green light

  • The Neosho R-5 Board of Education approved a bid on tuckpointing at Central Elementary and sealing and painting exterior walls at South Elementary.
    • email print
      Comment
  • The Neosho R-5 Board of Education approved a bid on tuckpointing at Central Elementary and sealing and painting exterior walls at South Elementary.
    The board awarded a $74,000 bid for the work to MTS Contracting, with the Central work estimated at $51,500 and the work at South School estimated at $22,500.
    The other bidder was Branco Enterprises, which estimated the work for the two projects at $135,000, with $79,000 allotted for the work at Central and $56,000 for the South School project.
    Throughout the school year, the buildings and grounds department goes over district facilities, noting maintenance and repairs that need to be made during the summer. Including a roof on a portion of South School (see story in Tuesday’s paper), and the aforementioned work at Central and South, nearly $500,000 worth of summer maintenance projects are slated for the school district.
    Funds are budgeted each year for maintenance projects. Other projects approved by the school board Monday night included:
    • Carpet replacement to tile and asbestos abatement at South Elementary, $18,162.50;
    • Asphalt for phase 1 of renovations to the bus barn, estimated at $150,000;
    • A classroom divider and wall system at the ag building, $15,845;
    • Carpet replacement to tile and asbestos abatements at Central Elementary, $17,032;
    • Marquees at South and Benton, $15,000;
    • Security cameras, primarily at the middle school, $35,000.
    Small projects include:
    Benton
    • Add woodchips in the playground safety fall zones;
    • Paint as time permits;
    • Strip and wax classrooms and hallways, extract carpeted areas;
    Carver
    • Add woodchips in the playground safety fall zones;
    • Strip and wax classrooms and hallways, extract carpeted areas;
    • Paint as time permits.
    Central
    • Add woodchips in the playground safety fall zones;
    • Strip and wax classrooms and hallways, extract carpeted areas;
    • Paint as time permits.
    Field
    • Add woodchips in the playground safety fall zones;
    • Strip and wax classrooms and hallways, extract carpeted areas;
    • Paint as time permits.
    Goodman
    • Add woodchips in the playground safety fall zones;
    • Strip and wax classrooms and hallways, extract carpeted areas;
    • Paint as time permits.
    South
    • Add woodchips in the playground safety fall zones;
    • Strip and wax classrooms and hallways, extract carpeted areas;
    • Paint as time permits.
    High school
    Page 2 of 2 - • Strip and wax classrooms and hallways, extract carpeted areas;
    • Paint as time permits;
    • Junior high office carpet replacement;
    • Vo-ag building dividing wall system replacement.
    Jefferson Street campus (formerly the Alternative School)
    • Strip and wax classrooms and hallways, extract carpeted areas;
    • Paint as time permits;
    • Exterior concrete steps.
    Middle school
    • Add gravel in the safety fall zones;
    • Strip and wax classrooms and hallways, extract carpeted areas;
    • Paint as time permits.
    The board also approved a change order for a new scoreboard at the softball field.

        calendar